This paint is a water-based interior paint that is made mainly of acrylic emulsion resin and pigment excellent in hiding power. It is designed to be suitable for painting the ceilings of a building. In particular, it is an interior water-based product that can minimize uneven brightness caused by painting tools due to its low gloss.
Surface treatment :
1. The material should be sufficiently cured (cured more than 30 days at 20℃)
2. Laitance, dust, oil and other contaminants on the surface must be completely removed.
3. The proper pH of the material must be less than 9, and the percentage of moisture content must be less than 6%.
4. The gaps and grooves on the surface must be filled with exterior water-based putty, and surface adjustment should be made before coating.
Coating method :
1. Primer
① For concrete/cement substrates, after surface treatment, dilute the water-based permeable sealer DNX-4001 up to 100%, if necessary, and apply once to get a dry film thickness of 15㎛ with a roller or brush.
② For areas where the absorption of the surface is severe, apply once more coating.
2. Top Coat
① After at least 3 hours at 20℃ following undercoating, apply this paint twice to get a dry film thickness of 60㎛ with a brush, roller or spray.
② At this time, apply by diluting with water up to 20%.
③ After 2 coats, the re-coating interval is at least 3 hours after the first top coating at 20℃.
This paint is a water-based interior paint that is made mainly of acrylic emulsion resin and pigment excellent in hiding power. It is designed to be suitable for painting the ceilings of a building. In particular, it is an interior water-based product that can minimize uneven brightness caused by painting tools due to its low gloss.
Surface treatment :
1. The material should be sufficiently cured (cured more than 30 days at 20℃)
2. Laitance, dust, oil and other contaminants on the surface must be completely removed.
3. The proper pH of the material must be less than 9, and the percentage of moisture content must be less than 6%.
4. The gaps and grooves on the surface must be filled with exterior water-based putty, and surface adjustment should be made before coating.
Coating method :
1. Primer
① For concrete/cement substrates, after surface treatment, dilute the water-based permeable sealer DNX-4001 up to 100%, if necessary, and apply once to get a dry film thickness of 15㎛ with a roller or brush.
② For areas where the absorption of the surface is severe, apply once more coating.
2. Top Coat
① After at least 3 hours at 20℃ following undercoating, apply this paint twice to get a dry film thickness of 60㎛ with a brush, roller or spray.
② At this time, apply by diluting with water up to 20%.
③ After 2 coats, the re-coating interval is at least 3 hours after the first top coating at 20℃.
This paint is a water-based interior paint that is made mainly of acrylic emulsion resin and pigment excellent in hiding power. It is designed to be suitable for painting the ceilings of a building. In particular, it is an interior water-based product that can minimize uneven brightness caused by painting tools due to its low gloss.
Surface treatment :
1. The material should be sufficiently cured (cured more than 30 days at 20℃)
2. Laitance, dust, oil and other contaminants on the surface must be completely removed.
3. The proper pH of the material must be less than 9, and the percentage of moisture content must be less than 6%.
4. The gaps and grooves on the surface must be filled with exterior water-based putty, and surface adjustment should be made before coating.
Coating method :
1. Primer
① For concrete/cement substrates, after surface treatment, dilute the water-based permeable sealer DNX-4001 up to 100%, if necessary, and apply once to get a dry film thickness of 15㎛ with a roller or brush.
② For areas where the absorption of the surface is severe, apply once more coating.
2. Top Coat
① After at least 3 hours at 20℃ following undercoating, apply this paint twice to get a dry film thickness of 60㎛ with a brush, roller or spray.
② At this time, apply by diluting with water up to 20%.
③ After 2 coats, the re-coating interval is at least 3 hours after the first top coating at 20℃.